470 infra projects report ‘cost overrun’ of Rs 4.38L cr

Must Read



The Flash Report on Central sector projects for April published by the Ministry of Statistics and Programme Implementation showed that 525 projects are running behind schedule.

Out of the 1,737 projects, only 11 projects are ahead of schedule, 213 are on schedule, showed the report.

“Total original cost of implementation of the 1737 projects was 22,33,409.53 crore and their anticipated completion cost is likely to be 26,71,440.77 crore, which reflects overall cost overruns of 4,38,031.24 crore (19.61 per cent of original cost),” it said.

The expenditure incurred on these projects till April 2021 is just over Rs 13.16 lakh crore, which is 49.26 per cent of the anticipated cost of the projects, as per the ministry’s report.

It, however, added that the number of delayed projects decreases to 375 if delay is calculated on the basis of latest schedule of completion. Further, for 988 projects neither the year of commissioning nor the tentative gestation period has been reported.

Disclaimer: This story is auto-aggregated by a computer program and has not been created or edited by FreshersLIVE.Publisher : IANS-Media



Source link

- Advertisement -spot_img

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -spot_img
Latest News

oru yamandan premakadha tamil dubbed movie download isaimini moviesda tamilrockers tamilyogi kuttymovies Trends on Google

oru yamandan premakadha tamil dubbed movie download Isaimini People have started to search oru yamandan premakadha tamil dubbed movie...
- Advertisement -spot_img

More Articles Like This

- Advertisement -spot_img